Vale Begins Commissioning Serra Sul +20 Project to Add 20 Million Tons of Annual Capacity
Brazilian mining giant starts up long-distance conveyor belt at S11D operation as part of strategy to reach 360 million tons of iron ore production by 2030.
Vale Advances Major Capacity Expansion
Vale S.A. announced it has commenced commissioning of the long-distance conveyor belt for its Serra Sul +20 project, marking the beginning of the start-up phase for the major capacity expansion at its S11D iron ore operation in Canaã dos Carajás, Pará, Brazil (6-K filing, 2026-07-31).
The project is expected to add 20 million tons per year of production capacity and increase operational flexibility at S11D, one of the world's most competitive iron ore operations. Together with the Compact Ore Crusher project, scheduled to start up in the fourth quarter of 2026, Serra Sul +20 represents a significant milestone in Vale's production expansion strategy (6-K filing, 2026-07-31).
Strategic Importance for Global Supply
"The Serra Sul +20 is a strategic project that further strengthens our position at S11D, one of the most competitive iron ore operations in the industry," said Gustavo Pimenta, Vale's CEO. "It also increases the iron ore business operational flexibility and enhances our ability to offer high-grade products to the market" (6-K filing, 2026-07-31).
Pimenta emphasized that the project is part of the Novo Carajás Program, which aims to sustain iron ore production and expand the supply of high-quality iron ore and critical minerals, "reinforcing Brazil's role in the global energy transition and creating long-term value for society and our stakeholders" (6-K filing, 2026-07-31).
Project Scope and Timeline
The Serra Sul +20 project comprises the expansion of mine and plant capacity at S11D through several initiatives, including the duplication of the long-distance conveyor belt, development of new mining areas, installation of a new semi-mobile crushing system, and implementation of additional processing lines at the plant. The project received its mining operating license in September 2025 (6-K filing, 2026-07-31).
Together with the Capanema and VGR1 projects, Serra Sul +20 represents "important milestones in Vale's plan to sustainably increase iron ore production to approximately 360 Mt by 2030, while enhancing the flexibility of its iron ore product portfolio" (6-K filing, 2026-07-31).
Company Context
Vale S.A., with a market capitalization of approximately $64 billion, is one of the world's largest iron ore producers. The company's shares last closed at 76.28 on the Brazilian exchange. According to MarginX data, Vale is scheduled to report its third-quarter 2026 results on October 29, 2026, with an earnings call the following day.
The filing was signed by Marcelo Feriozzi Bacci, Executive Vice President for Finance and Investor Relations, and includes standard forward-looking statement disclaimers regarding risks and uncertainties related to countries of operation, global economy, capital markets, mining and metals prices, and global competition (6-K filing, 2026-07-31).